Stop guessing how long tasks take - use PERT to estimate with confidence. Enter optimistic, most likely, and pessimistic durations for each task and get statistically reliable estimates instantly.
Data-Driven Estimation
Use PERT-based estimates to set realistic deadlines, negotiate scope with clients, and deliver on time - every time.
Set deadlines based on statistical estimates, not gut feel
See which tasks have the highest uncertainty at a glance
Share estimates with your team and stakeholders instantly
Identify scope creep early with confidence ranges
Back up your timelines with data, not promises
Allocate the right people to the right tasks based on estimates
Pro Tip
In Worklenz, these estimates attach directly to real project tasks - track actual vs estimated duration and improve your planning over time.
Our PERT calculator helps project managers and freelancers produce defensible estimates that account for uncertainty - so you stop missing deadlines and start delivering with confidence.
Pro Tip
Start with your riskiest tasks first. High uncertainty estimates are where your project schedule is most vulnerable.
Free trial • No credit card required • Easy setup
Everything you need to know about PERT estimation and task duration planning
PERT (Program Evaluation and Review Technique) is a statistical method for estimating task durations. It uses three estimates - optimistic, most likely, and pessimistic - to calculate an expected duration using the formula: (O + 4M + P) / 6. This produces a weighted average that accounts for uncertainty and is far more reliable than single-point estimates.
For each task, enter three duration estimates: Optimistic (best-case), Most Likely (realistic), and Pessimistic (worst-case). The calculator computes the PERT expected duration, standard deviation, and 95% confidence range. Add all your tasks to see the total project duration with combined uncertainty.
The 95% confidence range (Expected ± 2×SD) means there is a 95% probability the actual duration will fall within this range. For example, if the expected duration is 10 hours with a 95% range of 7–13 hours, you can be 95% confident the task will take between 7 and 13 hours.
A HIGH uncertainty warning appears when the standard deviation is more than 20% of the expected duration. This means your optimistic and pessimistic estimates are far apart relative to the expected value - the task is risky and the estimate is unreliable. Consider breaking the task into smaller pieces or gathering more information.
The project-level combined standard deviation is calculated as the square root of the sum of all individual task variances (SD²). The project 95% range is then: Total Expected ± 2 × Combined SD. This gives you a statistically valid confidence interval for the entire project duration.
Yes, your data is completely safe. All calculations happen locally in your browser. Your task data is stored only in your browser's localStorage and is never sent to any server. You can even use this tool offline after the first load.